Saturday, April 23, 2005

Yet ANOTHER summary

-gui functionality very nearly complete (could add input checks and other refinements)
-bugs worked out

Friday, April 08, 2005

Another summary

  • gui mostly functional now
  • (The above due to lots of coding and testing over the last few weeks)

Thursday, March 24, 2005

10:30 - Sum up activities

Suffice it to say that I have been very busily engaged in the Project Tracker. The main work has focused on the gui.
I would estimate a good 100 hours at least, since the last blog.

Friday, February 04, 2005

3:00 - 3:20 Team/Prof Meeting

  • Met with the professor for our weekly team/Prof/TA meeting

1:00 - 3:00 Team discussion

  • Talked about package organization
  • Talked about the tools that we need to familiarize ourselves with

Wednesday, February 02, 2005

12:00 - 5:00 SDS work and more Jigloo

  • Worked on my section of the SDS, "user interface issues"
  • Kept trying to get forms designed in jigloo, partially to see if I could use them to augment my section of the SDS

Tuesday, February 01, 2005

12:00 - 3:00 Familiarization with Eclipse, Jigloo

As we will be using Eclipse as our development environment, and Swing/Jigloo to help make the user interfaces, I did the following things.
  • Downloaded and Installed Eclipse, Jigloo
  • Familiarized myself with Eclipse and Jigloo
  • Began trying to develop Swing components using Jigloo

Monday, January 31, 2005

3:30 - 5:30 SDS Meeting

  • Met and decided on how the SDS would be divided amongst the team members
  • I got the job of describing the user interface issues section of section 2 of the SDS